CONSENT TO ESTABLISH ( How to get NOC) Go Back | Home Page

A1 (i) PROCEDURES FOR GRANT OF CONSENT TO ESTABLISH (NOC) :-

· The industrial units falling under 17 categories of highly polluting, 19 Category of polluting, additional polluting categories( as per categorization list ) & Other Large and Medium Industries including Additional Industries Beyond 17 & 19 Categories ( Annexure I ) shall apply for consent to establish (NOC) directly in the Head Office on the prescribed form along with necessary documents & requisite NOC fee in duplicate & each has to be signed by authorized signatory to avoid delay.

· The necessary documents, which are required to be submitted along with NOC application, are as under:

i) Scheme for pollution control including E.T.P APCM & HW management if application
ii) Site plan/layout plan (not applicable in case of industry located in approved industrial area)
iii) Project report
iv) Memorandum of Articles/ Partnership deed
v) NOC fee
vi) Flow Chart & Manufacturing Process
vii) Affidavit in respect of column 12.5,12.6, & 12.7 of NOC From applicable.

· The permission from the irrigation department for discharge of effluent into water bodies such as Rivers/Canals/Drains is required to those cases, which can adversely affect the quality of such water bodies.

· The NOC so granted shall be valid for period of two years to be extended for another one year at the discretion of the Board or till the time the unit starts its trial production whichever is earlier except for the stone crushers where it will be valid for 9 months as per notification no.S.O.126/C.A29/86/S.5 & 7197 dated 18th Dec, 1997 issued by Govt. of Haryana, Environment Deptt.

· However in case of specific projects like power plants, fertilizer Refineries etc. NOC shall be valid up to 4 years to extend for another one year at the discretion of the Board or till the time the unit starts its trial production whichever is earlier. No extra NOC fee will be charged for extension of NOC in this case.

Under the time bound grant of NOC the HSPCB has started issuing No objection Certificates from pollution angle to new industrial units except those where Public Hearing or Environment Management Plan is required within seven working days. The speedy NOC clearances would give a big boost to faster growth of industry in the State of Haryana.

· The objections, if any, will be conveyed to the applicants by obtaining a self-addressed envelop to eliminate the scope of misplacing their letters. In case the applicant fails to respond Board's queries then he will be given personal opportunity in the shape of hearing.